Outboard Trawler Build - Recap of Work Done
See also recap videos in 'Links' page
First Look - Fall 2018
'Wayne' answered our Kijiji ad looking for a small displacement hull. He had "inherited" this boat. The original owner had passed away after working on it for about 27 years.
Out With the Old
For a narrow, round-bilge hull, we found the cabin too high and too heavy. We decided to reconfigure the whole cabin and deck structure. We removed most of the old cabin structure.
Inboard Out
We removed and sold the old inboard engine, transmission, shaft and Prop. Our plan is to use a four-stroke outboard in a well.
Hauling to Iroquois, Ont.
First guy we hired didn't know what he was doing. "Toy Storage" did a fine job with the move.
Winter 2018-19
Delivered to Iroquois and wrapped for winter.
Winter Project
2018-19
We built ten laminated beams over the winter.
Spring 2019
In spring we built the motor well.
Turning over
It took us about a week to turn the boat over. Bottom work required this.
Photo missing in action.
Ooops!
Bottom Work
Thruster Tube
We picked up a bow thruster and installed the tube.
We refinished the gunnel boards, reconfigured the keel and finished the motor well.
New Bottom
Gelcoat removed. Three coats of epoxy and three coats of 'Interprotect' applied.
Fall 2019
Bottom painted, topsides painted and hull turned upright again.
Winter 2019-20
With leftover wood from the turning cradle, we built stairs. Wrapped for winter.
Items Acquired to Date
(February 2020)
Toilet, Sink, Stove, Anchors, Anchor Line, Bilge Pump, Bow Roller, Electrical Panels, Depth Sounder, Chartplotter, Cabin Door, Head Door, Ballast, Bow Thruster, Opening Hatches (2), Life Ring, Water Pump, Horn, Battery Boxes, Water Tanks, Fuel Tank and Windows.
Feb 2020 - Pre-Covid
We began in late winter as the weather started to warm.
​
Installed the lower half of all bulkheads.
March 2020 - Pre-Covid
Before the boatyard was closed by the Covid 19 lockdown, we managed to start the deck framing using laminated beams that we had made over the winter of 2018-2019.
May 2020
When the boatyard opened again, we made arrangements to be placed inside a covered shelter for the summer. For the move, we built a cradle under the hull.
We were happy to be under the shelter where we could work all summer, rain or shine, without having to wrap and unwrap tarps.
June 2020
In the shelter, work progressed quickly on the deck and cabin framing. MikeBro and Noreen came twice over the summer. Both times they spent a week and their help was much appreciated.
We finished the framing and attached cabin walls. We made the 'beamless' cabin top with balsa-core sandwiched between layers of thin plywood, all bonded with epoxy.
Early Summer 2020
Summer 2020
By mid-summer, we had finished laying the decking and building the main cabin structure, cabin top and pilothouse walls.
Next, we covered all the exterior plywood with fiberglass embedded in epoxy and covered with a layer of epoxy fairing putty.
Summer 2020
Late Summer 2020
Our final challenge of the fall was to create, install, fiberglass and putty the pilothouse roof.
Just before Thanksgiving Day, we emptied the boat of tools and equipment and covered it with a tarp. It doesn't need to be covered because of the weather, it's to protect the (as yet unpainted) epoxy from the sun's UV rays.
Fall 2020
October 2020
Our major task was to create window frame cover plates for all nine windows.
Additionally, we acquired more materials; steering system, VHF radio, plumbing and electrical components, instruments, safety gear, etc.
Spring '21 Pre-Covid Shutdown
Redesigned interior, installed wc and galley bulkheads, tabbed floor framing, installed ballast, purchased motor & controls, installed dash panels, fit steering, windows, cleats, bilge pump, and handrails, started painting bilge area.
Winter 2020/2021
Finished exterior including paint and non-skid. Did float test. Installed necessary electrics. Got license, survey and insurance. Test-floated and ran the motor on the last day of summer.
Fall '21 - It Runs!
Ran the boat to begin engine break-in schedule and test handling. Began work on the interior (fresh water tank, settee/bunk and WC walls), winterized the motor.
Summer '21 - It Floats!
Had settee cushions made. Purchased settee hardware, teak trim and teak dish holder. Made two dorade boxes. Purchased solar panel kit. Began work on forward battery box.
Spring '22
Installed bow thruster, dorade vents, solar panel, forward battery box, toilet, galley cabinet, head cabinet, fridge and navigator seat. sailed home to BYC (2 days). Painted interior, began building seatbacks for settees.
Winter '21-'22
Summer 2022 Interior Work Continues
Summer 2022 (continued) Meanwhile, We Enjoy the Boat
Fall 2022
Hauled out early due to unusually low water and in preparation for changing all the floating docks in the harbour.
Steel Cradle
Concerned about high winds blowing 'Helen Back' off the stands, we acquired a steel cradle and managed to maneuver it into place under the boat.
Winter 2022
We wrapped the boat with an extra tarp at the stern to protect the big tarp from being thrashed by the strong south-west winds at the waterfront.
Dinghy
We built a 'stitch-and-glue' dinghy over the winter (2022), in the hope that it will be useful as we 'anchor out' while cruising this summer of '23.